Back to Landscaping tools

Rip Rap Calculator

Work out how much rip rap (riprap) you need — in US tons (tonnes) and cubic yards (m³) — to armour a slope against erosion, from the bank length, slope run and ratio, and the rock layer thickness. Accounts for the extra area of the slope, picks a thickness by rip rap class, and adds a voids allowance. Add a price per ton for the cost. Everything runs on your device.

Guide: How Much Rip Rap Do I Need? (Erosion Control)

Slope & area

RunRiseRiprapThickness2:1
Sloped area481.4 ft²

Riprap layer

Rock size
Riprap to order
26.03 ton
481.4 ft² of slope at 11.81 in 19.3 yd³ incl. 10% voids.
Armoring several slopes? Add each for one combined tonnage below.
Sloped area
481.4 ft²
Volume
19.3 yd³
Slope factor
× 1.1

Buy list — whole job

Armoring more than one slope? Press Add to buy list on each — the combined tonnage and volume total up here.

Add these quantities to a quote

Sends 2 line items to the quote builder — just add your prices.

Rock layer only — plan the filter and toe

This is the riprap stone itself. You also need a filter layer — geotextile fabric or a graded bedding stone — under it so the bank does not wash out through the gaps, and a keyed-in toe trench at the bottom so the armour cannot slide. The optional flow-sizing uses the Isbash equation — a first-pass estimate for straight, uniform banks and channels; steep chutes, bridge scour or large rivers need HEC-11 / USACE methods and an engineer.

Tip: the slope factor is why armouring a bank takes more rock than its flat footprint — a 2:1 slope is about 12% more area than the ground it covers, a 1:1 slope over 40% more. Order by the ton and place largest stones first at the toe.

Questions & answers

Everything you need to understand the rip rap calculator.

How much rip rap do I need?

Work out the sloped area (bank length × slope length), multiply by the layer thickness for the volume, then by the placed density for the tonnage. A 33 ft long, 13 ft run 2:1 slope (10 m × 4 m run) is about 480 sq ft (45 m²) of face; at a 12 in (300 mm) light-class layer that is roughly 18 yd³ (14 m³), or about 25 US tons (22 t) at 1.6 t/m³ with a 10% voids allowance. The calculator does the slope maths and the units for you.

How does the slope affect how much rip rap I need?

Riprap covers the sloped face, which is longer than the flat ground it sits on — the “slope factor”. A 2:1 slope has about 12% more surface area than its footprint, a 1.5:1 slope about 20% more, and a 1:1 slope over 40% more. Enter the run and the slope ratio and the calculator scales the area up automatically, so you do not come up short.

How thick should a rip rap layer be?

A common rule is 1.5–2 times the median stone size (D50): about 12 in (300 mm) for 6 in stone, 18 in (450 mm) for 9 in stone, 24 in (600 mm) for 12 in stone. The calculator’s class presets set a typical thickness; on a designed job the D50 and thickness come from the water velocity, so follow the drawing.

What size rip rap do I need for the water velocity?

Bigger, faster water needs bigger stone. A common first-pass is the Isbash equation: D50 = V² ÷ (C² × 2g × (Sg − 1)), where V is the flow velocity, Sg the rock’s specific gravity (~2.65), g gravity, and C an Isbash coefficient set by turbulence (about 1.2 for a plain bank, 0.86 for turbulent flow near a structure). Switch the calculator to “Size from flow”, enter the velocity, turbulence and specific gravity, and it works out the required D50 and layer thickness, then the tonnage. It is an estimate for straight, uniform banks — steep chutes, bridge scour or big rivers need HEC-11 / USACE methods and an engineer.

What is D50 and rip rap class?

D50 is the median stone size — half the rock by weight is larger, half smaller. Riprap is sold in graded classes (by D50 or by DOT class names) so the mix of sizes locks together and resists being washed out. Bigger, faster water needs a larger D50 and a thicker layer. Pick the class and the calculator uses its typical thickness.

Do I need filter fabric under rip rap?

Almost always. A geotextile filter fabric (or a graded bedding-stone layer) goes under the riprap so the soil beneath cannot wash out through the gaps between the stones, which would undermine the armour. Also key the bottom row into a toe trench so the layer cannot slide down the slope. The calculator includes the fabric area in the quote hand-off.

ExequtechOS

Do the whole job in one place

A calculation is just the start. ExequtechOS takes it from estimate to quote, job card, invoice and paid — for your whole team.

Get started with ExequtechOS
  • Turn these numbers into a client-ready quote
  • Job cards, invoicing & inventory in one place
  • Works offline in the field, syncs when you’re back